Introduction
On May 10, 2010, the Supreme Judicial Court (SJC) issued a
decision which interpreted the application of the commonwealth's
public construction competitive bidding laws to a situation in
which a public university contracted with a private party for the
development and maintenance of a newly constructed dormitory, by
entering into a long-term lease. In Brasi Development Corp. v.
Atty Gen.,1 the SJC found that based on the broad
statutory language appearing in G.L. c. 149, § 44A (2)(D), the
public construction bidding laws apply to the construction "of any
building" undertaken by a public agency, even if the property in
question is actually owned by a private party.
Thus, the SJC determined that in circumstances such as those
involved here, a long-term lease between a public agency and a
private developer may be subject to the strict requirements for
soliciting bids and awarding public construction contracts as
specified in the competitive bidding laws, where it is established
that the public agency retains significant control over the
construction process.
The decision is important in that it provides some guidance to
public awarding authorities, contractors who bid on public works
and to the Attorney General's Office, which enforces the
competitive bidding law requirements.
Statutory framework
The commonwealth's public construction bidding laws 2
provide the means for awarding authorities to obtain the lowest
price that competition among qualified contractors can secure and
serve to establish an open and honest procedure for fair
competition among bidders for public contracts. St. 1980, c. 579, §
55; St. 2004, c. 193. Section 44A (2)(D) of G.L. c. 149 requires
that "[e]very contract for the construction, reconstruction,
installation, demolition, maintenance or repair of any building by
a public agency …" must be awarded using the specific procedures
set forth in G.L. c. 149, §§ 44A to 44H.
As part of this comprehensive statutory scheme, the public
construction bid laws include requirements for certification and
prequalification of contractors, intended to further the
legislative goals of fairness and accountability.3
Before a prospective contractor may submit a bid, the contractor
must be prequalified by the Division of Capital Asset Management
(DCAM) in order to certify the prospective bidder's financial
status, experience and other information related to qualifications
and responsibility.
DCAM issues certificates to eligible contractors, which indicate
dollar limits for the projects on which they bid, to ensure that
applicants are capable of undertaking such
construction.4 Where a construction project is estimated
to exceed $10 million, additional pre-certification requirements
apply.5 Only contractors who are pre-certified are
deemed responsible and eligible bidders who may participate in the
process.
The attorney general is responsible for ensuring that the
competitive bidding system is faithfully carried out and that
public contracts comply with public construction bidding
requirements. The attorney general initiates investigations into
potential violations through a proceeding known as a "bid protest
hearing," in which the attorney general issues a written decision,
including factual findings and determinations.6 At the
conclusion of an investigation, the attorney general may elect to
seek judicial enforcement of bid protest decisions.7
Events surrounding Brasi's proposal to the University
of Massachusetts, Lowell
The University of Massachusetts, Lowell (UML), part of the
publicly-funded state university system, wanted to expand the
campus housing available to its student population within the city
of Lowell.
The plaintiff, Brasi Development Corp. (Brasi), a private property
development firm, had not previously undertaken any student housing
projects, and was not certified by DCAM. Brasi incorporated in 2005
for the sole purpose of purchasing and developing a particular
parcel of land in Lowell, in close proximity to UML's campus. Brasi
purchased the parcel in 2006, and at some point had previously
approached UML about a project, but no agreement was reached.
During May 2007, Brasi obtained zoning approval from the city's
planning board to develop its property as a student dormitory. The
Court found that this change in zoning use provided Brasi with an
economically viable use of the property at the expiration of any
agreement with the university.
About eight months after Brasi received planning board approval,
during February 2008, UML issued a request for proposals (RFP) to
solicit bids for a privately developed housing facility for 120-400
students, located in close proximity to its campus. The RFP sought
a five-year lease with the potential to extend the agreement for
two additional five-year terms.
Although the RFP did not provide that the dormitory must be newly
constructed, it contained UML's design specifications for the
square footage of rooms, window placement, ratio of parking spaces
to apartment units, numbering system to be used for each room,
security system devices compatible with UML's network, the types
and placement of vending machines, and a design concept consistent
with the character of UML's existing architecture and with the City
of Lowell.
The RFP included a sample "lease agreement," and a general lease,
which reserved to UML the right to approve all improvements,
architectural design plans, construction materials and product
specifications. The sample agreement made future assignment of the
agreement contingent upon UML's written approval, and prohibited
granting any easement without UML's assent. The successful bidder
would also be required to give written notice before mortgaging the
property. The sample agreement granted UML a right of first refusal
to purchase the property, but that right was later waived.
The university would be responsible only for the lease payments,
but not for any construction costs. The RFP further specified that
the selected bidder would bear maintenance and repair costs for the
building and grounds during the lease, including snow and trash
removal and daily cleaning, and would assume all operation costs,
such as utility payments, Internet and cable access.
However, any subcontracting of these services required UML's
advance approval. In addition, the successful bidder would be
required to procure liability insurance coverage for the duration
of the project, with UML to be listed as an additional named
insured, and must provide advance notice before any insurance
cancellation could take effect.
The RFP contained an occupancy schedule, under which any
construction was to be completed within 15 months, and specified
that an occupancy date of either the fall of 2008 or August 2009
was a critical factor in selecting among the proposals. The
university would not be required to make any payments until the
dormitory was available for occupancy, and there were substantial
penalties if the selected bidder failed to meet the deadline.
Although the bidding process was open, the RFP did not comply with
the competitive bidding procedures set forth in G.L. c. 149, §§
44A-44H. Moreover, the RFP expressly stated that the contract would
not necessarily be awarded to the lowest-priced responsible
bidder.
UML received seven responses to the RFP, including one from Brasi.
Three of the proposals, including Brasi's submission, were for new
construction, while the remainder proposed to renovate and convert
existing structures. Two bidders proposed structures without any
modifications.
Brasi indicated its estimated construction costs to be at least
$25 million. On May 9, 2008, UML selected Brasi's submission,
subject to various additional conditions not included in the RFP.
These conditions included a provision for UML to have the right for
full review and approval of the site plans, and that Brasi hire a
consultant approved by UML, or that UML be given greater control
and sign-off on the project, including the right to attend weekly
progress meetings during construction. On May 12, 2008, Brasi
accepted UML's conditions.
The attorney general's investigation
In response to a notice of protest, the attorney general
initiated an investigation to determine whether UML's proposal to
build a student housing facility was subject to the public
construction bid laws. The attorney general held a bid protest
hearing on June 11, 2008, attended by representatives of UML and
the protestors.
While the attorney general's bid protest was pending, during
August 2008, UML and Brasi executed a lease agreement, in which the
university would be obligated to pay annual rent of $1,702,000 for
the first year of the agreement with subsequent increases up to
$1,920,636 by the fifth year, exclusive of management and
maintenance payments. The subsequent rent payments would be
negotiated. The agreement was for an initial five-year term,
renewable every five years at UML's option, for a total of 30
years. Under the agreement, Brasi remained the property
owner.
On Aug. 13, 2008, the attorney general issued a bid protest
decision, allowing the protest, based on the attorney general's
determination that the contemplated dormitory project is subject to
the public construction bid laws. Based on the attorney general's
bid protest decision, UML sent a notice to Brasi intending to
terminate their agreement on Aug. 20, 2008. Brasi filed the instant
declaratory judgment action. The attorney general counterclaimed,
seeking a determination that the bid protest decision be upheld.
The parties agreed to resolve the matter through submission of
cross-motions for summary judgment.
Court's legal analysis
The issue before the Court was essentially whether the
commonwealth's public construction bid laws8 apply when
a public agency enters into a contract with a private entity to
build a facility on private property, where the public agency
retained significant control over the construction process.
In beginning its analysis in Brasi, the Court noted that
in the context of other similar competitive bidding statutes, such
as public procurement and public works, the SJC had previously
found such competitive bidding laws may be broad enough to
encompass long-term leases between public agencies and private
parties.9 The Court noted, however, that a determination
as to whether a lease is subject to competitive bidding is a
fact-specific analysis, which cannot be based on any one single
factor.
The SJC continued on in its analysis to expressly agree with the
Appeals Court's most recent use of a multi-factor test in
Andrews v. Springfield,10 decided under the
same competitive construction bid law at issue in Brasi, G.L. c.
149, § 44A (2)(D). In Andrews, the Appeals Court concluded
that the City of Springfield's long-term lease agreement for the
construction of an animal shelter was construction of a building by
a public agency for purposes of the competitive bidding laws.
Without explicitly setting a new test to determine the application
of the public construction bidding laws, the Appeals Court in
Andrews considered several factors to be significant in
support of its decision: 1) the length of the lease term; 2) the
awarding authority's detailed design and construction requirements;
3) the degree of the awarding authority's control of the
construction process; and 4) the fact that the lease payments were
more than the costs of constructing the building.
In reaching its conclusion, the Appeals Court also relied on the
awarding authority's express intention, as stated in its RFP, that
it sought to acquire an animal control facility for its long-term
use, and to ultimately purchase the property at the end of the
lease term, thus obtaining ownership of the facility through public
funds. While agreeing with the Appeals Court's analysis and
conclusion reached in Andrews, the SJC held that no
specific set of facts will be sufficient for every situation. Thus,
the Court adopted a totality of the circumstances test, which takes
into account the unique circumstances of each case.
The SJC found the following factors to be useful, but not
dispositive, in determining the application of competitive bidding
requirements to "build to lease" agreements: 1) the degree of
control the public agency retains during development and
construction of the project; 2) the length of the lease, including
any extensions; 3) whether public funds will be expended; 4)
whether payments made under the agreement will essentially cover
the construction costs; 5) whether, at the end of the lease term,
the public agency retains a purchase option for a nominal sum, or
the property would otherwise be automatically transferred to the
public agency; 6) whether the public agency, which initially owned
the property, sold or leased it to the private party, or the agency
had a building constructed and then leased the newly constructed
building; and 7) whether the building is of such a specialized
nature that it would be unsuitable for another commercial purpose
without significant renovations.
The Court noted that if the terms of the RFP here were considered
in isolation, then the project would not have been subject to
competitive bidding. The Court expressly found many of the RFP's
design requirements to be common and not indicative of a
specialized level of design.11 Moreover, although the
RFP's provisions for the electrical system and security features
were particular to meet the needs of the university, the Court
noted that some level of customization of leased space is common
and a tenant's involvement in that process will not convert a lease
into a public construction agreement.
Nevertheless, the Court ultimately held that certain material
differences between the terms of the RFP and the lease agreement
which the university entered into with Brasi were critical to the
determination that the public construction bidding laws
applied.
The Court found several factors to be material in reaching this
conclusion: 1) the project here involved creation of a new
building; 2) located adjacent to the university's campus and
dependent on the use of the university's own existing parking lot;
3) for which the university would grant to Brasi easements of
unlimited duration; 4) the university had the right to occupy the
building for 30 years, double the amount of time under the RFP; and
5) the increased degree of UML's supervision over the construction
process from that provided in the RFP, specifically the
university's contractual right to attend weekly construction
meetings and to approve and monitor the various phases of the work
in progress.12
Prospective impact
Brasi clearly establishes that a public agency does not
fall outside of the jurisdiction of the construction bid laws
merely by contracting to lease privately owned property. Underlying
the legislatively mandated objectives to ensure fair and open
competition for public projects, Brasi contemplates that leases
which directly or indirectly use public resources to facilitate
construction may be subject to the competitive procurement
process.
Such competitive bid requirements may apply where an existing
building will undergo extensive renovation to meet the needs of the
prospective public tenant, even if the lease will not require
"ground up" construction. For example, if a long-term lease
requires that the landlord will make additions to an existing
facility, it may be more likely deemed a construction project
subject to public bidding. Conversely, it appears that when "build
out" activities undertaken by the prospective landlord are limited
in scope, involve only cosmetic changes, or when temporary public
use is clearly intended, the lease is less likely to implicate the
construction procurement laws.13
By adopting the attorney general's longstanding "totality of the
circumstances test," Brasi requires consideration of
various factors, including whether the public tenant exercises
significant control over the construction process, the degree to
which the lease payments are designed to recoup construction costs,
and other indicia that the public agency is actually using the
leasing mechanism as a means to construct a facility for its use
with the ultimate objective of attaining ownership. Therefore, the
particular characteristics of the public agency's RFP and resulting
lease necessarily must be reviewed.
A public body otherwise subject to competitive bidding
requirements would be well advised to consider whether its
construction requirements as part of any lease with a private party
would be deemed subject to the construction bid laws.14
To the extent to which an RFP would appear likely to implicate the
construction bid laws, a public agency should integrate terms and
conditions into an RFP and lease which clearly describe the public
agency's obligations for procurement compliance and notify
prospective landlords and developers that they must assume such
obligations.
Public agencies planning to issue an RFP for the lease of office
space or any other facility are encouraged to review their plans
with the Office of the Attorney General well in advance of
publishing their solicitation, in order to discuss the likelihood
that its specifications could be found to implicate the
construction bid laws.15 Such a prospective review may
also involve an analysis of whether the leasing arrangements are
subject to other statutory procedures governing leasing, even where
no construction is contemplated. For example, cities and towns are
subject to G.L. c. 30B, § 16 when acquiring rental space at a cost
exceeding $25,000.
Karla E. Zarbo is an assistant attorney general in the
Fair Labor Division of the Massachusetts Attorney General's Office,
where she has handled civil, criminal and administrative
enforcement matters for the last 12 years. She primarily focuses on
appellate litigation. Previously, she specialized in insurance
fraud litigation at Smith & Brink PC in Quincy.
Brian C. O'Donnell is an assistant attorney general in the Bid Unit
of the Fair Labor Division of the Attorney General's Office. He
handles bid protests and investigations, as well as inquiries from
contractors and public officials regarding the application and
interpretation of the commonwealth's public construction bidding
laws.
*Karla E. Zarbo was counsel of record in
Brasi Development Corp. v. Atty Gen., 456
Mass. 684 (2010). Nevertheless, this article represents the
opinions and legal conclusions of its authors and not necessarily
those of the Office of the Attorney General.
Opinions of the Attorney General are formal documents rendered
pursuant to specific statutory authority; this article is not
intended to be an official Opinion of the Attorney General rendered
pursuant to statutory authority.
1456 Mass. 684 (2010).
2G.L. c. 149, §§ 44A-44H (West 2010).
3G.L. c. 149, §§ 44D-44D½ (West 2010).
4G.L. c. 149, § 44D (3); 810 C.M.R. 8.03 (West
2010).
5G.L. c. 149, § 44D½ (West 2010).
6G.L. c. 149, § 44H (West 2010).
7Id.
8G.L. c. 149, §§ 44A-44H (West 2010).,
9See, e.g., Datatrol, Inc. v. State Purch.
Agent, 379 Mass. 679, 688 n. 7 (1980) (state lottery's
agreement to lease computer system was found to actually be a
purchase agreement subject to the general procurement law, G.L. c.
7, § 22, where public agency retained purchase option at end of
lease term).
1075 Mass. App. Ct. 678 (2009),
11Cf. Andrews, 75 Mass. App. Ct. at 680-81
(city-controlled design specifications by hiring architect to
develop detailed design and construction specifications,
incorporated in RFP, and required bidders to comply with
them).
12In light of the university's acknowledged urgent need
for student housing, the Court found these factors to suggest that
UML intended to exercise indefinite use of the dormitory.
13This approach is consistent with the attorney
general's bid protest decisions, finding the construction bid laws
inapplicable in circumstances where the lease term was capped by
statute to 10 years and the facility was intended to be used
temporarily while construction of the public agency's permanent
facility was underway.
14Moreover, although not addressed in Brasi,
the same considerations appear to apply to the long-term leasing of
land for development of public works projects, typically governed
by G.L. c.30, § 39M (e.g., athletic fields, running
tracks, parking facilities).
15It would also be advisable to consult with the
Division of Occupational Safety regarding the possible
applicability of the commonwealth's prevailing wage laws, G.L. c.
149, §§ 26-27H, inclusive.